Project Description
Replacement of Quay Wall at Kabil, Batam, Indonesia
Project Information
- Bored Pile: 1000mm – 135 nos
- Secant Bored Pile: 1500mm – 211 nos
Client:
PT SMOE (subsidiary of SEMBCORP Industries Singapore)
Engineer:
POSFORD Haskoning SDN BHD
Main Contractor:
LOH & LOH Construction PTE LTD / PT Juta Adi Usaha
Year:
Dec-05 to July-06