Project Description

Improvement to Bukit Timah first diversion canal (Holland Green to Clementi Road).

Project Information

  • Contiguous Bored Pile: 1000mm – 100 nos
  • Pre-bore deck/King Posts: 800mm – 1200mm – 85 nos

Client:

Public Utilities Board

Engineer:

CH2MHILL/KTP Consultants Pte Ltd

Main Contractor:

United Singapore Builders Pte Ltd

Year:

Jun-16 to Jul-17